Posted

Just out of curiosity, is there any logic to the order the 129f's are processed in? First come first served, alphabetically by height, anything?

Thanks

January 15, 2012 met on line

April 18, 2012 met in person in Cebu

April 20, 2012 proposed

May 28, 2012 filed K1

June 6, 2012 received email K1 accepted.

August 28, 2012 NOA2 approved!!!!!!!

September 21, 2012 went back for vist number 2

Had a wonderful time!

Interview set for November 6

Flying out November 3 to be together

Arrived November 4

November 6, 2013 interview and approved

November 14, 2013 picked up visa!

November 29, 2013 arrived in Anchorage

November 30, 2013 applied for marriage license

December 15, 2013 civil wedding

February 16, 2013 AOS filed

February 23, 2013 NOA 1 reviewed

April 4, 2013 Biometric appointment

May 9, 2013 AOS intervie

May 9, 2013 Approved ap, ead and green card

May 18, 2013 received Green Card, EAD and AP in mail

Posted

They play darts and the file they hit is the one they work on next.

England.gif England!

And in this crazy life, and through these crazy times

It's you, it's you, You make me sing.

You're every line, you're every word, you're everything.

b0cb1a39c4.png

ROC Timeline

Sent: 7/21/12

NOA1: 7/23/12

Touch: 7/24/2012

Biometrics: 8/24/2012

Card Production Ordered: 3/6/2013

*Eligible for Naturalization: October 13, 2013*

Filed: K-1 Visa Country: Philippines
Timeline
Posted

Exactly what I thought! Government logic! I love it! This must be the example they will use to administer health care! :help:

January 15, 2012 met on line

April 18, 2012 met in person in Cebu

April 20, 2012 proposed

May 28, 2012 filed K1

June 6, 2012 received email K1 accepted.

August 28, 2012 NOA2 approved!!!!!!!

September 21, 2012 went back for vist number 2

Had a wonderful time!

Interview set for November 6

Flying out November 3 to be together

Arrived November 4

November 6, 2013 interview and approved

November 14, 2013 picked up visa!

November 29, 2013 arrived in Anchorage

November 30, 2013 applied for marriage license

December 15, 2013 civil wedding

February 16, 2013 AOS filed

February 23, 2013 NOA 1 reviewed

April 4, 2013 Biometric appointment

May 9, 2013 AOS intervie

May 9, 2013 Approved ap, ead and green card

May 18, 2013 received Green Card, EAD and AP in mail

Filed: AOS (apr) Country: Denmark
Timeline
Posted

They play darts and the file they hit is the one they work on next.

I though they'd have a bobcat machine, blindfold an employee and put him in the room with boxes. First box he'd knock down would be first box to work on. While they might not do that yet, I'd wish they read VJ and take that up at their next meeting, then film it and post it on VJ to say that they do in fact take requests seriously.

K1 process, October 2010 > POE, July 2011

I-129F approved in 180 days from NOA1 date. (195 days from filing to NOA2 in hand)

Interview took 224 days from I-129F NOA1 date. (241 days from filing petition until visa in hand)

From filing I-129F petition until POE: 285 days

Click timeline or "about me" for all details.

AOS process, December 2011 > July 2012

EAD/AP Approval took 51 days from NOA1 date to email update. (77 days from filing until EAD/AP in hand)

AOS Approval took 206 days from NOA1 date to email update. (231 days from filing until greencard in hand)

From filing I-129F petition until greencard in hand: 655 days

Click timeline or "about me" for all details.

Filed: AOS (apr) Country: Denmark
Timeline
Posted

(OP, have a look at this link; http://www.visajourney.com/content/adjudicator-q-and-a - it just took me a while to fint it for you)

K1 process, October 2010 > POE, July 2011

I-129F approved in 180 days from NOA1 date. (195 days from filing to NOA2 in hand)

Interview took 224 days from I-129F NOA1 date. (241 days from filing petition until visa in hand)

From filing I-129F petition until POE: 285 days

Click timeline or "about me" for all details.

AOS process, December 2011 > July 2012

EAD/AP Approval took 51 days from NOA1 date to email update. (77 days from filing until EAD/AP in hand)

AOS Approval took 206 days from NOA1 date to email update. (231 days from filing until greencard in hand)

From filing I-129F petition until greencard in hand: 655 days

Click timeline or "about me" for all details.

Filed: IR-1/CR-1 Visa Country: Vietnam
Timeline
Posted
Filed: AOS (apr) Country: Philippines
Timeline
Posted

No logic whatsoever

Sent I-129 Application to VSC 2/1/12
NOA1 2/8/12
RFE 8/2/12
RFE reply 8/3/12
NOA2 8/16/12
NVC received 8/27/12
NVC left 8/29/12
Manila Embassy received 9/5/12
Visa appointment & approval 9/7/12
Arrived in US 10/5/2012
Married 11/24/2012
AOS application sent 12/19/12

AOS approved 8/24/13

Filed: Citizen (apr) Country: Jamaica
Timeline
Posted

Sigh.

K1
VSC NOA1 --- March 8, 2012
NOA2 --- October 11, 2012
Visa Approved --- December 17, 2012
POE --- December 22, 2012

AOS
AOS/EAD/AP NOA1 --- March 4, 2013
Biometrics --- April 3, 2013

EAD/AP received --- May 16, 2013

AOS Interview --- August 9, 2013

GC in production --- August 9, 2013

GC received --- August 17, 2013

N400

Approved May, 2018

Oath May, 2018

I130 - Nebraska SC

NOA1 - August 30, 2018

Case approved - August 28, 2019

NVC -

Interview -



I am the USC who brought my fiancé here on a K1,  who's now a USC and is now filing for his mother - whose case just got approved :)

Filed: AOS (pnd) Country: Argentina
Timeline
Posted

hahaha, you made me laugh!

We sent our I129F in December and by June we had our NOA2

Luck maybe??

Hope the same happens with the new petition

Day 0 08/21/2012 Sent I-130, I-485, I-765 and I-131

Day 1 Received the next day via UPS

Day 6 08/27/2012 email and text for all 4

Day 10 08/31/12 NOA1 for all 4 and Biometric appointment for 09/21

Day 18 09/08/12 REF on I-485, waiting for the letter

Day 31 09/21/12 Biometrics done

Day 34 09/24/12 RFE hard copy for I-864

Day 51 10/11/12 RFE Response sent (about 30 days behind)

Day 55 10/15/12 RFE response review

Day 64 10/24/12 Online status changed to EAD/AP Card production

Day 72 11/01/12 EAD/AP Card arrived!!

Day 73 11/02/12 Interview SMS for December 3rd

Day 76 11/05/12 Applied for SSN and HARD COPY of Interview

Day 104 12/03/12 INTERVIEW DAY!!! 9 am Chicago, IL

Filed: AOS (apr) Country: Philippines
Timeline
Posted

Just out of curiosity, is there any logic to the order the 129f's are processed in? First come first served, alphabetically by height, anything?

Thanks

I DON'T THINK IF ITS ALPHABETICALLY ITS FIRST COME FIRST SERVE NOT IN ALPHABETICALLY ORDER...

ADJUSTMENT OF STATUS

Filing date: April 23, 2011

I-485 Biometrics Appt Date: May 16,2011

I-485 Approval Date:June 26 , 2011

I-485 Approved: Approved

Green Card received Date: August 04,2011

Filed: IR-1/CR-1 Visa Country: Colombia
Timeline
Posted

Petitions are said to be processed in the order they are received, I don't think it says they are adjudicated in the order they are received. An important factor has to be the country where the beneficiary will have their interview. All consulates cannot handle the same amount of interviews each day, week, or month. Anybody that has called USCIS should realize that they run interference, they may say something different every time, but basically they say, "Wait longer before you call us again". Is just my theory, but I think petitions are approved or denied a lot faster than we would think, and USCIS finally releases them to NVC in a steady rate so that interviews may be scheduled and such. There are said to be no numerical limits to the amount of spousal and fiancee visas that may be issued, but I'm sure the number is not unlimited, or determined by the amount of petitions awaiting interviews.

Filed: Lift. Cond. (apr) Country: China
Timeline
Posted

Moved from K1 Process & Procedures to USCIS Service Centers forum; topic is about USCIS operations and not about the visa process itself.

Our journey:

Spoiler

September 2007: Met online via social networking site (MySpace); began exchanging messages.
March 26, 2009: We become a couple!
September 10, 2009: Arrived for first meeting in-person!
June 17, 2010: Arrived for second in-person meeting and start of travel together to other areas of China!
June 21, 2010: Engaged!!!
September 1, 2010: Switched course from K1 to CR-1
December 8, 2010: Wedding date set; it will be on February 18, 2011!
February 9, 2011: Depart for China
February 11, 2011: Registered for marriage in Wuhan, officially married!!!
February 18, 2011: Wedding ceremony in Shiyan!!!
April 22, 2011: Mailed I-130 to Chicago
April 28, 2011: Received NOA1 via text/email, file routed to CSC (priority date April 25th)
April 29, 2011: Updated
May 3, 2011: Received NOA1 hardcopy in mail
July 26, 2011: Received NOA2 via text/email!!!
July 30, 2011: Received NOA2 hardcopy in mail
August 8, 2011: NVC received file
September 1, 2011: NVC case number assigned
September 2, 2011: AOS invoice received, OPTIN email for EP sent
September 7, 2011: Paid AOS bill (payment portal showed PAID on September 9, 2011)
September 8, 2011: OPTIN email accepted, GZO number assigned
September 10, 2011: Emailed AOS package
September 12, 2011: IV bill invoiced
September 13, 2011: Paid IV bill (payment portal showed PAID on September 14, 2011)
September 14, 2011: Emailed IV package
October 3, 2011: Emailed checklist response (checklist generated due to typo on Form DS-230)
October 6, 2011: Case complete at NVC
November 10, 2011: Interview - APPROVED!!!
December 7, 2011: POE - Sea-Tac Airport

September 17, 2013: Mailed I-751 to CSC

September 23, 2013: Received NOA1 in mail (receipt date September 19th)

October 16, 2013: Biometrics Appointment

January 28, 2014: Production of new Green Card ordered

February 3, 2014: New Green Card received; done with USCIS until fall of 2023*

December 18, 2023:  Filed I-90 to renew Green Card

December 21, 2023:  Production of new Green Card ordered - will be seeing USCIS again every 10 years for renewal

 

 
Didn't find the answer you were looking for? Ask our VJ Immigration Lawyers.

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
- Back to Top -

Important Disclaimer: Please read carefully the Visajourney.com Terms of Service. If you do not agree to the Terms of Service you should not access or view any page (including this page) on VisaJourney.com. Answers and comments provided on Visajourney.com Forums are general information, and are not intended to substitute for informed professional medical, psychiatric, psychological, tax, legal, investment, accounting, or other professional advice. Visajourney.com does not endorse, and expressly disclaims liability for any product, manufacturer, distributor, service or service provider mentioned or any opinion expressed in answers or comments. VisaJourney.com does not condone immigration fraud in any way, shape or manner. VisaJourney.com recommends that if any member or user knows directly of someone involved in fraudulent or illegal activity, that they report such activity directly to the Department of Homeland Security, Immigration and Customs Enforcement. You can contact ICE via email at Immigration.Reply@dhs.gov or you can telephone ICE at 1-866-347-2423. All reported threads/posts containing reference to immigration fraud or illegal activities will be removed from this board. If you feel that you have found inappropriate content, please let us know by contacting us here with a url link to that content. Thank you.
×
×
  • Create New...