I was unable to sign in the NVC website,is this a sign of case completion.

I'm on the same situation as you are today. Lets wait and see what this means.

USCIS I-130 for Parents

08/27/2008 - Send I130 to Chicago LockBox

09/01/2008 - NOA1

09/09/2008 - Check cashed

09/11/2008 - Touched

12/22/2008 - Case transfered to California SC

12/23/2008 - Touched

12/30/2008 - Touched

12/31/2008 - Touched

01/02/2009 - Touched

01/08/2009 - NOA2 email for my father - got approved after 128 days of receiving NOA1

01/12/2009 - NOA2 email for my mother - got approved after 132 days of receiving NOA1

---0--- NVC Journey (not rushing) ---0---

01/12/2009 - father's case entered into the system

01/15/2009 - mother's case entered into the system

01/16/2009 - father's ds3032 and AOS bill generated

01/21/2009 - email father's ds3032

01/22/2009 - mother's ds3032 and AOS bill generated

01/23/2009 - email mother's ds3032

01/23/2009 - paid AOS bill online

01/28/2009 - father's ds3032 accepted (after 8 days of sending the email)

01/29/2009 - mother's ds3032 accepted (after 7 days of sending the email)

04/30/2009 - sent ds-230 with documents

05/08/2009 - sign-in Failed

05/11/2009 - case completed both parents

06/15-16/2009 - medical

07/07/2009 - interview. PASSED!!! THANK GOD!!!

??/??/2009 - visa received

Filed: K-3 Visa Country: Canada
Timeline
Posted

Noticed the same thing today as well. Called NVC this evening and operator said case was under "final review" and should be complete very soon.

Timeline

06/19/2004 - Married

09/16/08 - I-130 NOA1

10/03/08 - I-129F NOA1

10/06/08, 10/7/08, 10/20/08, 10/21/08 - Touches on the I-130

10/08/08 - I-129F touched

12/06/08 - Senator sent inquiry, both applications touched

04/03/09 - Called USCIS and initiated service request

04/14/09 - Both applications touched

04/15/09 - NOA2 notification received for both I-130 and I-129F (via email)

NVC (IR-1)

04/21/09 - NVC received and assigned case number

04/23/09 - Received DS-3032 form letter via email / AOS bill generated

04/23/09 - Sent DS-3032 via email

04/24/09 - Sent DS-3032 via FedEx (just in case)

04/27/09 - NVC received DS-3032 (AVR updated)

04/29/09 - Received IV Fee agent email, paid both AOS and IV bills online

04/30/09 - Both IV and AOS fee bills show as PAID online

04/30/09 - Sent AOS and IV packages via FedEx overnight

05/01/09 - AOS and IV packages delivered to NVC

05/05/09 - AVR says "NVC received your documents and they are under review..."

05/08/09 - Sign in no longer works on Payment Center site, operator says case is under final review

05/11/09 - Case complete!

06/23/09 - Interview date assigned - August 12th

08/12/09 - Interview ... Approved!

08/17/09 - Visa in hand - Delivered via Canada Post

08/28/09 - Moving day

Filed: Citizen (apr) Country: Morocco
Timeline
Posted

yes it means your case will be completed soon, many of us got the same message and the next day we got our case completed

[size="2"][font="Arial"][size="1"][u][b][color="#800080"][i]Naturalization Journey[/i][/color][/b][/u][i]
[color="#800080"]05/05/2012: N-400 sent [/color][color="#800080"]05/07/2012: USCIS received package
05/08/2012: Priority date
05/10/2012: NOA date
05/11/2012: Electronic notification from USCIS / Check cashed
05/14/2012: NOA received
05/23/2012: Biometrics notice received
06/08/2012: Early Biometrics (appointment scheduled for 06/14)
07/03/2012: [/color][color="#800080"]Electronic notification:[/color][color="#800080"]placed in line for interview scheduling
07/05/2012:[/color][/i][/size][/font][i][font="Arial"][size="1"][color="#800080"] Electronic notification: [/color][/size][/font][font="Lucida Sans Unicode"][color="#800080"][font="Arial"][size="1"]scheduled for interview
07/09/2012: Interview notice received
08/13/2012: Interview
[/size][/font][/color][/font][/i][/size][i][size="2"][font="Arial"][size="1"][color="#800080"]08/27/2012: [/color][color="#800080"]Electronic notification:[/color][color="#800080"]placed in line for oath scheduling[/color][/size][/font][/size]
[size="2"][font="Lucida Sans Unicode"][color="#800080"][font="Arial"][size="1"]08/29/2012: Oath notice recei[size="1"]ved [/size][/size][/font][/color][/font][/size][size="1"][color="#800080"]( no status update )
09/11/2012: Oath ceremony
[/color][/size]
[/i] [i] [/i] [i] [/i][size="2"][i] [/i][/size]

Filed: IR-1/CR-1 Visa Country: Pakistan
Timeline
Posted

Congratssss.........all u got their sign on failure......First sign on failure ever that makes us happy :)

Yes...it is a sign of case completion....it will be completed in a 1-2 days now

Mar 4,06 I-130 sent ,rcvd Mar 7,06

Oct 24,08 USC, called to Upgrade

Nov 1,08 Citizenship certificate sent

Jan 3,09 Case upgraded.

Jan 6,09 TOUCHED!!!

Feb 13,09 Approved : )

Feb 20,09 Case # assigned

Mar 2,09 bill paid online,DS-3032 emailed

Mar 4,09 NVC recvd fee

Mar 10,09 AOS sent

Mar 30,09 mailed DS-230

Apr 13,09 CASE COMPLETED(per operators)

Apr 20,09 FINAL REVIEW

Apr 21,09 CASE COMPLETED (per AVR)

Apr 23,09 called:INTERVIEW JUNE 24th

Jun 24,09 AP, 1-3 months

Calling DOS begins,here is what I was told

Jul 7,09 No info @ DOS

Jul 10,09 Case sent to DC-pending

Jul 17,09 Pending

Jul 24,09 Pending,you can call every day for update but the day they call him for passport it means something is up so you get to know it before we do

Jul 31,09 Pending AP

Aug 06,09 Call from USEM requesting to submit passport

Aug 07,09 Every thing looks very good,visa issuance is up to the consulate!!!

Aug 07,09 Passport submitted

Aug 07,09 USEM is requesting applicant's passport :)

Aug 17,09-call 1 Visa issued Aug 3rd,EM recvd passport on 10th but still havent returned it

Aug 17,09-call 2 Case pending some kind of processing (URGHHHHHHHHH NOT AGAIN)

Aug 18,09 call to pick up passport,picked up from AMEX

Sep 26,09 REUNION :)

Filed: IR-1/CR-1 Visa Country: Pakistan
Timeline
Posted
I was unable to sign in the NVC website,is this a sign of case completion.

how do i sign into the website ? i have my case #

You need ur IIN as well

here is the link

www.immigrantvisas.state.gov

Mar 4,06 I-130 sent ,rcvd Mar 7,06

Oct 24,08 USC, called to Upgrade

Nov 1,08 Citizenship certificate sent

Jan 3,09 Case upgraded.

Jan 6,09 TOUCHED!!!

Feb 13,09 Approved : )

Feb 20,09 Case # assigned

Mar 2,09 bill paid online,DS-3032 emailed

Mar 4,09 NVC recvd fee

Mar 10,09 AOS sent

Mar 30,09 mailed DS-230

Apr 13,09 CASE COMPLETED(per operators)

Apr 20,09 FINAL REVIEW

Apr 21,09 CASE COMPLETED (per AVR)

Apr 23,09 called:INTERVIEW JUNE 24th

Jun 24,09 AP, 1-3 months

Calling DOS begins,here is what I was told

Jul 7,09 No info @ DOS

Jul 10,09 Case sent to DC-pending

Jul 17,09 Pending

Jul 24,09 Pending,you can call every day for update but the day they call him for passport it means something is up so you get to know it before we do

Jul 31,09 Pending AP

Aug 06,09 Call from USEM requesting to submit passport

Aug 07,09 Every thing looks very good,visa issuance is up to the consulate!!!

Aug 07,09 Passport submitted

Aug 07,09 USEM is requesting applicant's passport :)

Aug 17,09-call 1 Visa issued Aug 3rd,EM recvd passport on 10th but still havent returned it

Aug 17,09-call 2 Case pending some kind of processing (URGHHHHHHHHH NOT AGAIN)

Aug 18,09 call to pick up passport,picked up from AMEX

Sep 26,09 REUNION :)

Filed: Citizen (pnd) Country: India
Timeline
Posted
I was unable to sign in the NVC website,is this a sign of case completion.

Yes, your case should be completed in a day or two!! Good Luck!!

The Journey Home
04/27/2009 - POE at JFK (Quick and Easy!!!!)
05/07/2009 - Applied for SSN
05/09/2009 - Welcome Letter Received
05/14/2009 - SSN Received
05/11/2009 - GC Production Ordered
06/12/2009 - GC Production Ordered (AGAIN ?!?!?!)
06/19/2009 - Alien Registration Approval notice email
06/22/2009 - 2 Year Green Card Received!!!!!!

Naturalization
02/06/2013 - Application Sent
02/13/2013 - NOA (Priority Date Feb 8th)
02/13/2013 - Biometrics Appt. Letter Received
02/21/2013 - Early Bio Appt. (Original March 15th)
02/26/2013 - Place Inline for Interview

04/24/2013 - Interview scheduled

05/31/2013 - Interview - Recommended for Approval

XX/XX/2013 - Oath Ceremony

 
Didn't find the answer you were looking for? Ask our VJ Immigration Lawyers.

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
- Back to Top -

Important Disclaimer: Please read carefully the Visajourney.com Terms of Service. If you do not agree to the Terms of Service you should not access or view any page (including this page) on VisaJourney.com. Answers and comments provided on Visajourney.com Forums are general information, and are not intended to substitute for informed professional medical, psychiatric, psychological, tax, legal, investment, accounting, or other professional advice. Visajourney.com does not endorse, and expressly disclaims liability for any product, manufacturer, distributor, service or service provider mentioned or any opinion expressed in answers or comments. VisaJourney.com does not condone immigration fraud in any way, shape or manner. VisaJourney.com recommends that if any member or user knows directly of someone involved in fraudulent or illegal activity, that they report such activity directly to the Department of Homeland Security, Immigration and Customs Enforcement. You can contact ICE via email at Immigration.Reply@dhs.gov or you can telephone ICE at 1-866-347-2423. All reported threads/posts containing reference to immigration fraud or illegal activities will be removed from this board. If you feel that you have found inappropriate content, please let us know by contacting us here with a url link to that content. Thank you.
×
×
  • Create New...