Filed: Timeline

Something isn't right here because they can't submit a service request for Jan12 until Jun12. The 5 months processing time hasn't reach there yet. And there computer won't allow it to submit a service request until the 5 months is over.

I am just baffled how you got them to submit a service request through and how they did it.

It was actually a tier 1 who submitted the request... because they said that they were processing Jan 16th and since that date was later than my priority date he was able to sumbit a request:

U.S. Department of Homeland Security

VERMONT SERVICE CENTER

75 LOWER WELDEN STREET

SAINT ALBANS,VT 05479

U.S. Citizenship and Immigration Services

Monday, May 7, 2012

Emailed to XXJAYM@GMAIL.COM

Dear ******:

On 05/01/2012 you, or the designated representative shown below, contacted us about your case. Some of the key information given to us at that time was the following:

Caller indicated they are:

-- Applicant or Petitioner

Attorney Name:

-- Information not available

Case type:

-- I130

Filing date:

-- 01/12/2012

Receipt #:

-- EAC-12-901-94***

Referral ID:

T1B1221203011VSC

Beneficiary (if you filed for someone else):

-- ****, Andrew

Your USCIS Account Number (A-number):

-- Information not available

Type of service requested:

-- Outside Normal Processing Times

The status of this service request is:

Our review indicates that this case is actually within our current processing time. We are currently processing cases filed on behalf of an immediate relative of a U.S. Citizen filed in November 2011. We regret any misunderstanding caused by our posted processing time report. If you do not receive a decision or notice of other action within our current processing time, check our website for an update or call customer service at the number provided below.

If you have any further questions, please call the National Customer Service Center at 1-800-375-5283.

Please remember: By law, every person who is not a U.S. citizen and who is over the age of 14 must submit Form AR-11 AND notify this office of their change of address, within 10 days from when they move (persons in "A" or "G" nonimmigrant status are exempt from this requirement). To notify this office of a move, visit our website at: www.uscis.gov or call the National Customer Service Center at 1-800-375-5283. The Form AR-11 can be downloaded from our website or you can call the National Customer Service Center at 1-800-375-5283 and we can order one for you. Instructions for filing the Form AR-11, including mailing instructions, are included on the Form.

U.S. Citizenship and Immigration Services

Met Through Mutual Friends: Early March 2009

Began dating: June 24th, 2010

Met in Manchester, England: October 20, 2010 to Oct 25, 2010

"Officially" became a couple: November 25, 2010

New Years together in England: Dec 26, 2010 to Jan 2, 2011

Visit to meet my family: February 19, 2011 to February 26, 2011

Visit to spend Easter/Spring Break together: April 16, 2011 to April 30, 2011

Spent the summer together in New York: June 23, 2011 to August 1, 2011

Came to visit just after my birthday: October 13, 2011 to October 23, 2011

Officially Announced Our Engagement: November 30, 2011

Trip to NY for New Years: December 27, 2011 to January 9, 2012

Wedding Day: January 4th, 2012

Trip to England & Italy for Valentine's Day: February 10, 2012 to February 20, 2012

Visit to NY for our 2 year dating anniversary: June 20th, 2012 to July 4th, 2012

Timeline

USCIS

01/08/2012: I-130 Sent from NY

01/11/2012: USPS Delivery Confirmation

01/12/2012: NOA1 E-mail & Text

XX/XX/2012: NOA2 E-mail & Text(STILL waitinggg... Ahhh!)

NVC

XX/XX/2012: NVC received

XX/XX/2012: Case number/IIN

XX/XX/2012: DS-3032 sent

XX/XX/2012: DS-3032 accepted

XX/XX/2012: AOS Bill PAID

XX/XX/2012: AOS Package sent

XX/XX/2012: IV Bill PAID

XX/XX/2012: IV Package sent

XX/XX/2012: Case complete at NVC

XX/XX/2012: Interview scheduled (Interview Date: XX/XX/2012)

US Embassy London

XX/XX/2012: Embassy received

XX/XX/2012: Medical

XX/XX/2012: Interview

XX/XX/2012: Visa

XX/XX/2012: POE Boston

Link to comment
Share on other sites

Filed: IR-1/CR-1 Visa Country: China
Timeline

im still baffled, then it must be a noob that submitted a SR within 5 months.

"Family time is very precious and you should cherish every moment of it."

01/20/12 - I-130 sent to Chicago Lockbox.

01/26/12 - NOA1 received and processing at Vermont.

06/28/12 - NOA2 announced on status check.

06/29/12 - NVC received case learned on 07/2/12.

06/30/12 - Hard copy NOA2 received.

07/09/12 - NVC Casefile Number and IIN Issued.

07/16/12 - Receive and Sent DS-3032 via email.

07/17/12 - Mailed DS-3032 via mail, AOS bill received via email, paid online, Optin email sent.

07/18/12 - Optin accepted and new case number, AOS marked paid, emailed AOS packet.

07/24/12 - Assigned as Agent, IV Fee bill received via email, paid online.

07/25/12 - IV Fee marked paid, emailed IV packet.

07/31/12 - Emailed GZO Supplemental Packet 3.

08/02/12 - Case completed and commenced final review.

08/03/12 - Shipped all copies of forms/letters/documents to my wife - arriving on 8/9/12.

08/06/12 - Case completed final review.

08/09/12 - Appointment letter received via email interview date set 9/6/12.

08/14/12 - Medical exam done.

08/15/12 - Medical exam results all normal.

09/06/12 - Submitted required documents at the embassy and interview set next day at 0730.

09/07/12 - Visa approved, click here for review http://www.visajourney.com/reviews/view-dos-cis-reviews.php?entry=10401 .

09/14/12 - Visa received on hand!

10/07/12 - Arrived at NYC! click here for review http://www.visajourney.com/reviews/view-poe-reviews.php?entry=15293

10/20/12 - Received welcome letter from USCIS.

10/25/12 - Green Card received!

"Nothing is more difficult than the art of maneuvering for advantageous positions." - Sun-Tzu

04/27/13 - Submitted DS-160 online for parent-in-laws and sister-in-law.

05/01/13 - Paid DS-160 or MRV Fee Payments on CGI Stanley.

05/03/13 - Made appointment for 05/16/13 on CGI Stanley.

05/16/13 - Arrived at GUZ and impromptu notice on the front it was closed.

05/30/13 - B2 visa interview passed! Read review here http://www.visajourney.com/forums/topic/433263-b2-visa-was-approved-for-parentinlaw/ <p>

"Good ideas are not adopted automatically. They must be driven into practice with courageous patience." - ADM Hyman G. Rickover

08/08/14 - Mailed I-175 application.

08/11/14 - I-175 arrived at VSC.

08/18/14 - Received NOA1 with date 08/12/14.

08/27/14 - Received biometrics appointment for 09/09/14.

02/27/15 - GC in production from email notification.

03/02/15 - Received NOA2 with approval dated 02/25/15.

Link to comment
Share on other sites

Is this really true that they're processing November?? OMg Please say its not so. Why would they just lie to people that they are working on Jan. I've been people within Jan & Feb getting approvals and theyre not DCF..

I'm so stressed and depressed, this is gonna kill me

Started Talking: 1998

Dated for 3 yrs, separated, & reunited after being apart for about 10yrs

Got married: Dec. 3rd, 2011

USCIS:

01/28/12 - I-130 Application filed and sent

02/07/12 - I-130 NOA1 Received neither email nor text.

07/12/12 - Received NOA2

NVC:

08/02/12 - Case number received

08/06/12 - Invoice ID Received

08/09/12 - Aos bill & Ds-3032 received

08/09/12 - AOS bill Paid

08/13/12 - Ds-3032 Accepted

08/15/12 - IV Bill received

08/15/12 - IV bill paid

08/23/12 - Case Completed

09/14/12 - Interview date:10/17/12

09/14/12 - checklist received

Link to comment
Share on other sites

Filed: IR-1/CR-1 Visa Country: China
Timeline

no chance of knowing and they process things in randomly.

"Family time is very precious and you should cherish every moment of it."

01/20/12 - I-130 sent to Chicago Lockbox.

01/26/12 - NOA1 received and processing at Vermont.

06/28/12 - NOA2 announced on status check.

06/29/12 - NVC received case learned on 07/2/12.

06/30/12 - Hard copy NOA2 received.

07/09/12 - NVC Casefile Number and IIN Issued.

07/16/12 - Receive and Sent DS-3032 via email.

07/17/12 - Mailed DS-3032 via mail, AOS bill received via email, paid online, Optin email sent.

07/18/12 - Optin accepted and new case number, AOS marked paid, emailed AOS packet.

07/24/12 - Assigned as Agent, IV Fee bill received via email, paid online.

07/25/12 - IV Fee marked paid, emailed IV packet.

07/31/12 - Emailed GZO Supplemental Packet 3.

08/02/12 - Case completed and commenced final review.

08/03/12 - Shipped all copies of forms/letters/documents to my wife - arriving on 8/9/12.

08/06/12 - Case completed final review.

08/09/12 - Appointment letter received via email interview date set 9/6/12.

08/14/12 - Medical exam done.

08/15/12 - Medical exam results all normal.

09/06/12 - Submitted required documents at the embassy and interview set next day at 0730.

09/07/12 - Visa approved, click here for review http://www.visajourney.com/reviews/view-dos-cis-reviews.php?entry=10401 .

09/14/12 - Visa received on hand!

10/07/12 - Arrived at NYC! click here for review http://www.visajourney.com/reviews/view-poe-reviews.php?entry=15293

10/20/12 - Received welcome letter from USCIS.

10/25/12 - Green Card received!

"Nothing is more difficult than the art of maneuvering for advantageous positions." - Sun-Tzu

04/27/13 - Submitted DS-160 online for parent-in-laws and sister-in-law.

05/01/13 - Paid DS-160 or MRV Fee Payments on CGI Stanley.

05/03/13 - Made appointment for 05/16/13 on CGI Stanley.

05/16/13 - Arrived at GUZ and impromptu notice on the front it was closed.

05/30/13 - B2 visa interview passed! Read review here http://www.visajourney.com/forums/topic/433263-b2-visa-was-approved-for-parentinlaw/ <p>

"Good ideas are not adopted automatically. They must be driven into practice with courageous patience." - ADM Hyman G. Rickover

08/08/14 - Mailed I-175 application.

08/11/14 - I-175 arrived at VSC.

08/18/14 - Received NOA1 with date 08/12/14.

08/27/14 - Received biometrics appointment for 09/09/14.

02/27/15 - GC in production from email notification.

03/02/15 - Received NOA2 with approval dated 02/25/15.

Link to comment
Share on other sites

Filed: Timeline

Has anyone called the VSC recently to get a date that they claim to be processing?

Not that I believe them, but I'm just wondering what they are telling other people....

They now just tell me "November 2011, like we told you in the e-mail" even though I know that isn't what they are telling people who call.. it's a date in late Jan, 2012 that most people are hearing.

I'm sure they are refusing to give me any more information becase they think I'm stupid and I'll just wait another 2-3 months just because they claim they are only to November, they just want me off their back...

Whatever, I'm just over 2 weeks away from 5 months and then I will have a congressman involved.

So yea, anyone have a "currently processing" date from the USCIS reps for VSC?

Met Through Mutual Friends: Early March 2009

Began dating: June 24th, 2010

Met in Manchester, England: October 20, 2010 to Oct 25, 2010

"Officially" became a couple: November 25, 2010

New Years together in England: Dec 26, 2010 to Jan 2, 2011

Visit to meet my family: February 19, 2011 to February 26, 2011

Visit to spend Easter/Spring Break together: April 16, 2011 to April 30, 2011

Spent the summer together in New York: June 23, 2011 to August 1, 2011

Came to visit just after my birthday: October 13, 2011 to October 23, 2011

Officially Announced Our Engagement: November 30, 2011

Trip to NY for New Years: December 27, 2011 to January 9, 2012

Wedding Day: January 4th, 2012

Trip to England & Italy for Valentine's Day: February 10, 2012 to February 20, 2012

Visit to NY for our 2 year dating anniversary: June 20th, 2012 to July 4th, 2012

Timeline

USCIS

01/08/2012: I-130 Sent from NY

01/11/2012: USPS Delivery Confirmation

01/12/2012: NOA1 E-mail & Text

XX/XX/2012: NOA2 E-mail & Text(STILL waitinggg... Ahhh!)

NVC

XX/XX/2012: NVC received

XX/XX/2012: Case number/IIN

XX/XX/2012: DS-3032 sent

XX/XX/2012: DS-3032 accepted

XX/XX/2012: AOS Bill PAID

XX/XX/2012: AOS Package sent

XX/XX/2012: IV Bill PAID

XX/XX/2012: IV Package sent

XX/XX/2012: Case complete at NVC

XX/XX/2012: Interview scheduled (Interview Date: XX/XX/2012)

US Embassy London

XX/XX/2012: Embassy received

XX/XX/2012: Medical

XX/XX/2012: Interview

XX/XX/2012: Visa

XX/XX/2012: POE Boston

Link to comment
Share on other sites

Filed: IR-1/CR-1 Visa Country: China
Timeline

the cust rep said they are working on jan23... it has been 1.5 weeks on that date.

"Family time is very precious and you should cherish every moment of it."

01/20/12 - I-130 sent to Chicago Lockbox.

01/26/12 - NOA1 received and processing at Vermont.

06/28/12 - NOA2 announced on status check.

06/29/12 - NVC received case learned on 07/2/12.

06/30/12 - Hard copy NOA2 received.

07/09/12 - NVC Casefile Number and IIN Issued.

07/16/12 - Receive and Sent DS-3032 via email.

07/17/12 - Mailed DS-3032 via mail, AOS bill received via email, paid online, Optin email sent.

07/18/12 - Optin accepted and new case number, AOS marked paid, emailed AOS packet.

07/24/12 - Assigned as Agent, IV Fee bill received via email, paid online.

07/25/12 - IV Fee marked paid, emailed IV packet.

07/31/12 - Emailed GZO Supplemental Packet 3.

08/02/12 - Case completed and commenced final review.

08/03/12 - Shipped all copies of forms/letters/documents to my wife - arriving on 8/9/12.

08/06/12 - Case completed final review.

08/09/12 - Appointment letter received via email interview date set 9/6/12.

08/14/12 - Medical exam done.

08/15/12 - Medical exam results all normal.

09/06/12 - Submitted required documents at the embassy and interview set next day at 0730.

09/07/12 - Visa approved, click here for review http://www.visajourney.com/reviews/view-dos-cis-reviews.php?entry=10401 .

09/14/12 - Visa received on hand!

10/07/12 - Arrived at NYC! click here for review http://www.visajourney.com/reviews/view-poe-reviews.php?entry=15293

10/20/12 - Received welcome letter from USCIS.

10/25/12 - Green Card received!

"Nothing is more difficult than the art of maneuvering for advantageous positions." - Sun-Tzu

04/27/13 - Submitted DS-160 online for parent-in-laws and sister-in-law.

05/01/13 - Paid DS-160 or MRV Fee Payments on CGI Stanley.

05/03/13 - Made appointment for 05/16/13 on CGI Stanley.

05/16/13 - Arrived at GUZ and impromptu notice on the front it was closed.

05/30/13 - B2 visa interview passed! Read review here http://www.visajourney.com/forums/topic/433263-b2-visa-was-approved-for-parentinlaw/ <p>

"Good ideas are not adopted automatically. They must be driven into practice with courageous patience." - ADM Hyman G. Rickover

08/08/14 - Mailed I-175 application.

08/11/14 - I-175 arrived at VSC.

08/18/14 - Received NOA1 with date 08/12/14.

08/27/14 - Received biometrics appointment for 09/09/14.

02/27/15 - GC in production from email notification.

03/02/15 - Received NOA2 with approval dated 02/25/15.

Link to comment
Share on other sites

I called today and they said that they cannot say any longer where they're currently processing.. Is this true? has anyone called lately?

Started Talking: 1998

Dated for 3 yrs, separated, & reunited after being apart for about 10yrs

Got married: Dec. 3rd, 2011

USCIS:

01/28/12 - I-130 Application filed and sent

02/07/12 - I-130 NOA1 Received neither email nor text.

07/12/12 - Received NOA2

NVC:

08/02/12 - Case number received

08/06/12 - Invoice ID Received

08/09/12 - Aos bill & Ds-3032 received

08/09/12 - AOS bill Paid

08/13/12 - Ds-3032 Accepted

08/15/12 - IV Bill received

08/15/12 - IV bill paid

08/23/12 - Case Completed

09/14/12 - Interview date:10/17/12

09/14/12 - checklist received

Link to comment
Share on other sites

  • 3 months later...
Filed: IR-1/CR-1 Visa Country: Morocco
Timeline

hiii everybody,

i just have and idea to add and i think it is logic.

we have to know that even the period they said it can take to get the approval , we have to put in consideration that every case has its circumstances, it doesnt mean that all people who are from the same country are going to be approved at the same time !! because each case has its won information and it may need more time to check !!

so just relax and take a deeep breath of patience while waiting for your approvals , since you got your NOA1, everything is fine ! all you need is just time.

hang in there.our time is coming sooon:) .God bless.

RtmM.png

as1cMaB-SeR0010MDAwMDA4fDAwMDEyNjdsfGZyb20gTk9BMSA.gif">

Link to comment
Share on other sites

 
Didn't find the answer you were looking for? Ask our VJ Immigration Lawyers.

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
- Back to Top -

Important Disclaimer: Please read carefully the Visajourney.com Terms of Service. If you do not agree to the Terms of Service you should not access or view any page (including this page) on VisaJourney.com. Answers and comments provided on Visajourney.com Forums are general information, and are not intended to substitute for informed professional medical, psychiatric, psychological, tax, legal, investment, accounting, or other professional advice. Visajourney.com does not endorse, and expressly disclaims liability for any product, manufacturer, distributor, service or service provider mentioned or any opinion expressed in answers or comments. VisaJourney.com does not condone immigration fraud in any way, shape or manner. VisaJourney.com recommends that if any member or user knows directly of someone involved in fraudulent or illegal activity, that they report such activity directly to the Department of Homeland Security, Immigration and Customs Enforcement. You can contact ICE via email at Immigration.Reply@dhs.gov or you can telephone ICE at 1-866-347-2423. All reported threads/posts containing reference to immigration fraud or illegal activities will be removed from this board. If you feel that you have found inappropriate content, please let us know by contacting us here with a url link to that content. Thank you.
×
×
  • Create New...