Oh I KNOW that everyone is capable of pulling up the stats and figures - but being a bit of a number cruncher
Anyway - as at today (25th November) -
K1 Visas sent in from
1st June through to 30th September
Total records sent = 625
Total of those with NOA-1's = 584 (lets keep our fingers crossed for the balance to get theirs SOON)
Total who have received NOA-2's = 134
Average number of days between filing and NOA-1 for that period = 15 (just as an FYI ours took 29)
Average number of days between NOA-1 & NOA-2 for that period = 122
Approvals (NOA-2's) so far (overall) for November is at 129 (with a week to go)
the number that were approved over the past couple of months..
October was 140
September was 80
August was 104
July was 61
June was 110
I used 1st June to 30th September (LOL because I am a Sept. filer <grin>) but also that overall period seems to be where the most congestion is occuring..
okie dokie LOL.. think I bored y'all enough.. back to my sunday morning now..